1.

In the critical path method of construction planning, Free Float can be_____________?_x005F_x000D_Consider the following statements ?_x005F_x000D_1. greater than Total Float._x005F_x000D_2. greater than Independent Float_x005F_x000D_3. equal to Total Float._x005F_x000D_4. less than Independent Float. Of these statements

A. 1 and 4 are correct
B. 2 and 3 are correct
C. 1 and 4 are correct
D. 1 and 2 are correct
Answer» C. 1 and 4 are correct