1.
In the coring process, at what speed is the barrel spun at?
A.
50 rpm
B.
500 rpm
C.
100 rpm
D.
250 rpm
Answer» C. 100 rpm
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Which type of auger is used for extracting the samples using the augering method?
The Shelby tube can be pushed further into the same hole to extract more sample.
A six-inch slot is cut in the trenching process to ______
______ is used in to cool the barrel in coring if sample at in-situ moisture content is desired.
The Shelby tubes can only be driven through unbound fine-grained soil layer.
In the bitumen extraction test, the test is performed until the colour of the extract is not darker than ______
______ sampling technique can be used for acquiring materials to determine the type and quantity of stabilizers for full-depth reclamation.
Which test is done to find the amount of bitumen in the pavement?
What is the size of the trench that is made for extracting samples?
Shelby tube samples can be used to determine the PVR value of materials. What does PVR mean?
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply