1.

In the bar chart planning____________?_x005F_x000D_Consider the following statements?_x005F_x000D_1. interdependence of the operations cannot be portrayed_x005F_x000D_2. progress of work can be measured_x005F_x000D_3. spare time of the activities can be determined_x005F_x000D_4. schedule cannot be updated

A. 1,2 and 3 are correct
B. 1 and 4 are correct
C. 2, 3 and 4 are correct
D. 1,2 and 4 are correct
Answer» C. 2, 3 and 4 are correct