1.

In an assembly line for assembling the engine, six workers are assigned tasks that take 22, 24, 26, 27, 25 and 26 minutes respectively. The balance delay for the line is:

A. 7.4%
B. 14.8%
C. 7%
D. 10.3%
Answer» B. 14.8%