1. |
In an AC network, the load connected is (10 + j10). The phase relation between the voltage applied and the current through the load is: |
A. | voltage and current are in phase with each other |
B. | voltage leads current by 45° |
C. | voltage lags current by 30° |
D. | voltage lags current by 45° |
Answer» C. voltage lags current by 30° | |