In a project, the contractor is paid on the basis of the running bill for a month. The rate contract for concreting is Rs. 1000/m of concrete. The consumption of number of cement of bags of weight 50 kg is 527. The mix proportion for the concrete is 1: 1.4 : 2.75 with W/C ratio of 0.52. The approximate billing amount of the month will be |
A. | Rs. 5, 27, 000 |
B. | Rs. 1.49, 404 |
C. | Rs. 62, 252 |
D. | Rs. 26, 350 |
Answer» B. Rs. 1.49, 404 | |