In a project logic, four activities , , and are required to be completed before starting activity . If the finish times of , , and are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity is

A. 12 days
B. 14 days
C. 15 days
D. 17 days
Answer» E.