| 1. |
If the variable overhead flexible budget variance is $26000 and the flexible budget amount is $15000, then the actual incurred costs will be |
| A. | $21,000 |
| B. | $11,000 |
| C. | $31,000 |
| D. | $41,000 |
| Answer» E. | |