If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________? |
A. | 50% |
B. | less than 50% |
C. | more than 50% |
D. | 100% |
Answer» D. 100% | |