If the manufacturing cycle efficiency is 0.725 and the total manufacturing time is 45 minute, then the value added manufacturing time will be |
| A. | 42.625 |
| B. | 36.724 |
| C. | 32.625 |
| D. | 41.625 |
| Answer» D. 41.625 | |