If the flexible budget amount is $26000 and fixed overhead flexible budget variance is $12500, then actual incurred cost would be |
| A. | $38,500 |
| B. | $48,500 |
| C. | $58,500 |
| D. | $13,500 |
| Answer» B. $48,500 | |