1.

If the budgeted price of input is $50, actual quantity of input is 150 units and the allowed budgeted quantity of input is 60 units then efficiency variance will be

A. $4,500
B. $3,500
C. $2,500
D. $1,500
Answer» B. $3,500


Discussion

No Comment Found