If the actual price input is $700, the budgeted price of input is $400 and the actual quantity of input are 50 units, then the price variance will be |
| A. | $15,000 |
| B. | $13,000 |
| C. | $11,000 |
| D. | $9,000 |
| Answer» B. $13,000 | |