If t is the duration of an activity, t 1 is the latest finish possible moment of its preceding activity and t 2 is the earliest start possible moment, the independent float of the activity is |
| A. | ( t 1 - t 2 ) - t |
| B. | t - ( t 1 - t 2 ) |
| C. | ( t 1 + t 2 ) - t |
| D. | t + ( t 1 - t 2 ) |
| Answer» B. t - ( t 1 - t 2 ) | |