If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good |
| A. | EF=ES+D |
| B. | LS=LF-D |
| C. | LF = LS + D |
| D. | all of the above. |
| Answer» E. | |