Activity s,lack or float of any event on a PERT/CPM chart is represented by |
| A. | latest start time of succeeding event -earliest finish time of preceding event activity time |
| B. | latest start time of the event - earliest start time of the event |
| C. | latest finish time of event - earliest finish time of the event |
| D. | all of the above |
| Answer» E. | |