MCQOPTIONS
Saved Bookmarks
This section includes 77 Mcqs, each offering curated multiple-choice questions to sharpen your GATE (Mechanical Engineering) knowledge and support exam preparation. Choose a topic below to get started.
1. |
After using a carbon dioxide fire extinguisher, the nozzle gets extremely cold.What does this indicate? |
A. | You should not use it. |
B. | The material inside is finished. |
C. | It is safe to continue. |
D. | The materials inside are running low |
Answer» B. The material inside is finished. | |
2. |
Queing theory is associated with |
A. | sales |
B. | inspection time |
C. | waiting time |
D. | production time |
Answer» D. production time | |
3. |
In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if |
A. | complete detailsof items in, waiting line are known |
B. | arrival and waiting times are known and can be grouped to form a waiting line model |
C. | all variables and constants are known and form a linear equation |
D. | the laws governing arrivals, service times, and the order in which the arriving units are taken into source are known |
Answer» E. | |
4. |
PERT is the |
A. | time oriented technique |
B. | event oriented technique |
C. | activity oriented technique |
D. | target oriented technique |
Answer» C. activity oriented technique | |
5. |
Which of the following equations is not in conformity with others |
A. | organisation performance x motivation = profits |
B. | knowledge x skill = ability |
C. | ability x motivation = performance |
D. | attitude x situation = motivation |
Answer» B. knowledge x skill = ability | |
6. |
Work study comprises following main techniques |
A. | method study and work measurement |
B. | method study and time study |
C. | time study and work measurement |
D. | method study and job evaluation |
Answer» B. method study and time study | |
7. |
A big advantage of PERT over Gantt charts is that in the former case |
A. | activities and events are clearly shown |
B. | early start and late finish of an acivity are clearly marked |
C. | activity times are clear |
D. | inter-relationship among activities is clearly shown. |
Answer» E. | |
8. |
PERT and CPM are |
A. | techniques to determine project status |
B. | decision making techniques |
C. | charts which increase aesthetic ap-pearance of rooms |
D. | aids to the decision maker. |
Answer» E. | |
9. |
Slack represents the difference between the |
A. | latest allowable time and the normal expected time |
B. | latest allowable time and the earliest expected time |
C. | proposed allowable time and the ear-liest expected time |
D. | normal allowable time and the latest expected time |
Answer» C. proposed allowable time and the ear-liest expected time | |
10. |
String diagram is used |
A. | for checking the relative values of various layouts |
B. | when a group of workers are working at a place |
C. | where processes require the operator to be moved from one place to another |
D. | all of the above |
Answer» E. | |
11. |
Replacement studies are made on the fol-lowing basis: |
A. | annual cost method |
B. | rate of return method |
C. | total life average method |
D. | any one of the above. |
Answer» E. | |
12. |
The linear programming techniques can be applied successfully to industries like |
A. | iron and steel |
B. | food processing |
C. | oil and chemical |
D. | all of the above. |
Answer» E. | |
13. |
In order that linear programming techniques provide valid results |
A. | relations between factors must be linear (positive) |
B. | relations between factors must be linear (negative) |
C. | (a) or (b) |
D. | only one factor should change at a time, others remaining constant |
Answer» D. only one factor should change at a time, others remaining constant | |
14. |
If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be |
A. | 2 HA |
B. | 1.33 HA |
C. | 1.5 HA |
D. | 1.15 HA |
Answer» B. 1.33 HA | |
15. |
According to Rowan plan, if H = hourly rate, A = actual time and S = standard time, then wages will be |
A. | HA |
B. | HA + (S~A) HA |
C. | HA + ^^-H |
D. | HA + ^^-H |
Answer» C. HA + ^^-H | |
16. |
The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as |
A. | Rowan Plan |
B. | Bedaux Plan |
C. | Taylor Differential Piece rate system |
D. | Halsey Premium plan |
Answer» E. | |
17. |
Which of the following plans motivates supervisors by paying a premium on time saved by workers |
A. | Halsey plan |
B. | Rowan plan |
C. | Haynes plan |
D. | Emersons plan |
Answer» D. Emersons plan | |
18. |
Which of the following is not wage incentive plan |
A. | differential piece rate System |
B. | Rowan plan |
C. | Emerson plan |
D. | Taylor plan |
Answer» E. | |
19. |
In Lincoln plan (one type of group incentive plan), the amount of the profit which an .employee receives in addition to the guaranteed basic pay/wages, is based on : |
A. | a standard rating system |
B. | a merit rating system |
C. | a job evaluation system |
D. | all of the above |
Answer» C. a job evaluation system | |
20. |
PERT has following time estimate |
A. | one time estimate |
B. | two time estimate |
C. | three time estimate |
D. | four time estimate |
Answer» D. four time estimate | |
21. |
CPM has following time estimate |
A. | one time estimate |
B. | two time estimate |
C. | three time estimate |
D. | four time estimate |
Answer» B. two time estimate | |
22. |
In the Halsey system of wage incentive plan, a worker is |
A. | paid as per efficiency |
B. | ensured of minimum wages |
C. | not paid any bonus till his efficiency 2 reaches 66 % |
D. | never a loser |
Answer» C. not paid any bonus till his efficiency 2 reaches 66 % | |
23. |
In the Halsey 50-50 plan, the following are rewarded more |
A. | past good workers |
B. | past poor workers |
C. | past average workers |
D. | all of the above |
Answer» C. past average workers | |
24. |
Which one of the following represents a group incentive plan ? |
A. | Scanlon Plan |
B. | Rowan Plan |
C. | Bedaux Plan |
D. | Taylor Differential Piece Rate System |
Answer» B. Rowan Plan | |
25. |
An optimum project schedule implies |
A. | optimum utilisation of men, machines and materials |
B. | lowest possible cost and shortest possible time for project |
C. | timely execution of project |
D. | to produce best results under given constraints |
Answer» C. timely execution of project | |
26. |
Routing is essential in the following type of industry |
A. | assembly industry |
B. | process industry |
C. | job order industry |
D. | mass production industry |
Answer» B. process industry | |
27. |
In Halsey 50-50 plan, output standards are established |
A. | by time study |
B. | from previous production records |
C. | from ones judgement |
D. | all of the above |
Answer» C. from ones judgement | |
28. |
The objective of time study is to determine the time required to complete a job by |
A. | fast worker |
B. | average worker |
C. | slow worker |
D. | new entrant |
Answer» C. slow worker | |
29. |
Current assets include |
A. | manufacturing plant |
B. | manufacturing plant and equipment |
C. | inventories |
D. | common stock held by the firm |
Answer» B. manufacturing plant and equipment | |
30. |
Tick the odd man out |
A. | Taylor |
B. | Drucker |
C. | McGregor |
D. | Galileo |
Answer» E. | |
31. |
The amount deducted from the salary of workers towards employees provident fund is |
A. | credited into reserves of company |
B. | deposited in nationalised bank |
C. | deposited in post office |
D. | deposited in the account of worker with Provident Fund Commissioner. |
Answer» E. | |
32. |
The employees provident fund act is applicable to |
A. | all industries |
B. | all industries other than small and medium industries |
C. | volunteers |
D. | the industries notified by Government |
Answer» E. | |
33. |
Which of the following layouts is suited to job production |
A. | process layout |
B. | product layout |
C. | fixed position layout |
D. | plant layout |
Answer» B. product layout | |
34. |
Pick up the incorrect statement about advantages of work sampling |
A. | permits a fine breakdown of activities and delays |
B. | simultaneous study of many operators may be made by a single observer |
C. | calculations are easier, method is economical and less time consuming |
D. | no time measuring devices are generally needed |
Answer» B. simultaneous study of many operators may be made by a single observer | |
35. |
Standard time as compared to normal time is |
A. | greater |
B. | smaller |
C. | equal |
D. | there is no such correlation |
Answer» B. smaller | |
36. |
Motion study involves analysis of |
A. | actions of operator |
B. | layout of work place |
C. | tooling and equipment |
D. | all of the above |
Answer» B. layout of work place | |
37. |
Material handling and plant location is analysed by |
A. | Gnatt chart |
B. | bin chart |
C. | Travel Chart |
D. | activity chart |
Answer» D. activity chart | |
38. |
Merit Rating is the method of determining worth of |
A. | a job |
B. | an individual employee |
C. | a particular division in workshop |
D. | machine |
Answer» C. a particular division in workshop | |
39. |
According to MAPI formula, the old machine should be replaced by new one when |
A. | CAM < DAM |
B. | CAM > DAM |
C. | CAM = DAM |
D. | there is no such criterion |
Answer» B. CAM > DAM | |
40. |
The term 'value' in value engineering refers to |
A. | total cost of the product |
B. | selling price of the product |
C. | utility of the product |
D. | manufactured cost of the product |
Answer» D. manufactured cost of the product | |
41. |
The technique of value analysis can be applied to |
A. | complicated items only |
B. | simple items only |
C. | crash-programme items only |
D. | any item. |
Answer» E. | |
42. |
Acceptance sampling is widely used in |
A. | batch production |
B. | job production |
C. | mass production |
D. | all of the above |
Answer» D. all of the above | |
43. |
The appellate authority for an industrial dispute is |
A. | management |
B. | labour court |
C. | high court/supreme court |
D. | board of directors |
Answer» D. board of directors | |
44. |
Statistical quality control techniques are based on the theory of |
A. | quality |
B. | statistics |
C. | probability |
D. | all of the above |
Answer» D. all of the above | |
45. |
In inventory control, the economic order quantity is the |
A. | optimum lot size |
B. | highest level of inventory |
C. | lot corresponding to break-even point |
D. | capability of a plant to produce |
Answer» B. highest level of inventory | |
46. |
Inventory management consists of |
A. | effective running of stores |
B. | state of merchandise methods of strong and maintenance etc. |
C. | stock control system |
D. | all of the above |
Answer» E. | |
47. |
Gnatt charts are used for |
A. | forecasting sales |
B. | production schedule |
C. | scheduling and routing |
D. | linear programming |
Answer» C. scheduling and routing | |
48. |
Which of the following is independent of sales forecast |
A. | productivity |
B. | inventory control |
C. | production planning |
D. | production control |
Answer» B. inventory control | |
49. |
Which of the following organisation is preferred in automobile industry |
A. | functional organisation |
B. | line organisation |
C. | staff organisation |
D. | line and staff organisations |
Answer» E. | |
50. |
The grouping of activities into organisational units is called |
A. | corporate plans |
B. | higher level management |
C. | functional authority |
D. | departmentatidn |
Answer» E. | |