*$_If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good? |
A. | EF = ES + D |
B. | LS = LF - D |
C. | LF = LS + D |
D. | All the above |
Answer» E. | |