1.

If Cp=Cpk which of these is true?

A. Process is centered at the LSL of the specifications
B. Process is centered at the USL of the specifications
C. Process is centered at the midpoint of the specification
D. Process is centered at the outside the specification limits
Answer» D. Process is centered at the outside the specification limits