1.

_If budgeted total direct labour hours are 3800 and budgeted direct labour cost is $480000, then budgeted direct labour cost rate will be$?

A. $126.32 per labour hour
B. $128.32 per labour hour
C. $130 per labour hour
D. $132 per labour hour
Answer» B. $128.32 per labour hour