

MCQOPTIONS
Saved Bookmarks
1. |
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is |
A. | (a + m + b)/6 |
B. | (a + 2m + b)/6 |
C. | (a + 4m + b)/6 |
D. | (a + 5m + b)/6 |
Answer» D. (a + 5m + b)/6 | |