MCQOPTIONS
Saved Bookmarks
| 1. |
High pressure grouting is generally restored for concreting in the lining if the rock strata is: |
| A. | highly fissured |
| B. | poor |
| C. | likely to get seepage of water |
| D. | All of the above. |
| Answer» E. | |