MCQOPTIONS
Saved Bookmarks
| 1. |
For transferring the tunnel alignment through shafts, we adopt the following steps : 1. Hanging two or more plumb lines in the shaft 2. Determining the bearing of the plumb lines i.e. plumb plane 3. Suspending a 35 kg weight by each plumb line 4. Immersing the weights of both the plumb lines in the buckets containing water. The correct sequence of steps is : |
| A. | 1 2 3 4 |
| B. | 4 3 2 1 |
| C. | l 3 2 4 |
| D. | 2 1 4 3 |
| Answer» B. 4 3 2 1 | |