				| 1. | For transferring the tunnel alignment through shafts, we adopt the following steps :1. Hanging two or more plumb lines in the shaft2. Determining the bearing of the plumb lines i.e. plumb plane3. Suspending a 35 kg weight by each plumb line4. Immersing the weights of both the plumb lines in the buckets containing water.The correct sequence of steps is : | 
| A. | 1 2 3 4 | 
| B. | 4 3 2 1 | 
| C. | l 3 2 4 | 
| D. | 2 1 4 3 | 
| Answer» B. 4 3 2 1 | |