MCQOPTIONS
Saved Bookmarks
| 1. |
For a foundation, find the elapsed time in which 90% of ultimate settlement will occur. The coefficient of consolidation is 4*10-4cm2/s. The average drainage path is 50cm. |
| A. | 56.38 days |
| B. | 43.78 days |
| C. | 61.34 days |
| D. | 78.23 days |
| Answer» D. 78.23 days | |