| 1. |
For a foundation, find the elapsed time in which 10% of ultimate settlement will occur. The coefficient of consolidation is 4*10-4cm2/s. The average drainage path is 50cm. |
| A. | 19.9 hours |
| B. | 15.5 hours |
| C. | 13.9 hours |
| D. | 17.5 hours |
| Answer» D. 17.5 hours | |