1.

For a company with an average daily demand of 9 units and a standard deviation of 3 units, a 9-day lead time, and a 95% service level, which of the following statements is true?

A. The reorder point is about 81 units
B. The safety stock is about 15 units
C. The reorder point is about 96 days.
D. The-reorder point is about. 81 days
Answer» B. The safety stock is about 15 units


Discussion

No Comment Found