For a certain loading condition, a saturated clay layer undergoes 40% consolidation in a period of 178 days. What would be the additional time required for further 20% consolidation to occur?

A. 89 days
B. 222.5 days
C. 267 days
D. 400.5 days
Answer» C. 267 days