1.

Five jobs need to be processed on a single machine. All the jobs are available for processing at time t = 0. Their respective processing times are given below.JobsIIIIIIIVVProcessing times (in minutes)13471411The mean completion time using the shortest processing time rule is _________ minutes.

A. 9.8
B. 24.2
C. 49
D. 121
Answer» C. 49