1.

Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour and work for 9500 actual hours at $110 per hour, then total cost would be

A. 2,078,000
B. 3,078,000
C. 2,065,000
D. 3,065,000
Answer» D. 3,065,000