Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be |
| A. | $2,078,000 |
| B. | $3,078,000 |
| C. | $2,065,000 |
| D. | $3,065,000 |
| Answer» D. $3,065,000 | |