1.

Consider the following statements :A critical activity in a CPM network has1. The longest duration of all activities2. zero total float3. zero for float4. The shortest duration of all activitieswhich one of the statements given above are correct ?

A. 1 and 2
B. 1 and 3
C. 2 and 3
D. 3 and 4
Answer» B. 1 and 3