Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is |
A. | 1, 2, 4, 3, 5 |
B. | 1, 3, 2, 4, 5 |
C. | 1, 2, 3, 4, 5 |
D. | 1, 3, 4, 2, 5 |
Answer» D. 1, 3, 4, 2, 5 | |