Consider a software project with the following information domain characteristic for calculation of function point metric.Number of external inputs (I) = 30Number of external output (O) = 60Number of external inquiries (E) = 23Number of files (F) = 08Number of external interfaces (N) = 02It is given that the complexity weighting factors for I, O, E, F and N are 4, 5, 4, 10 and 7, respectively. It is also given that, out of fourteen value adjustment factors that influence the development effort, four factors are not applicable, each of the other four factors have value 3, and each of the remaining factors have value 4. The computed value of function point metric is ______.

A. 612.06
B. 212.05
C. 305.09
D. 806.9
Answer» B. 212.05