A simple stand - alone software utility is to be developed in ’C’ programming by a team of software experts for a computer running Linux and the overall size of this software is estimated to be 20,000 lines of code. Considering (a, b) = (2.4, 1.05) as multiplicative and exponention factor for the basic COCOMO effort estimation equation and (c, d)=(2.5, 0.38) as multiplicative and exponention factor for the basic COCOMO development time estimation equation, approximately how long does the software project take to complete ? |
A. | 10.52 months |
B. | 11.52 months |
C. | 12.52 months |
D. | 14.52 months |
Answer» C. 12.52 months | |