1.

"Calculate the prime cost from the following information:Direct material purchased: Rs. 1,00,000.Direct material consumed: Rs. 90,000.Direct labour: Rs. 60,000.Direct expenses: Rs. 20,000.Manufacturing overheads: Rs. 30,000."

A. s. 1,80,000
B. s. 2,00,000
C. s. 1,70,000
D. s. 2,10,000
Answer» D. s. 2,10,000