| 1. |
*/*_"Calculate re-order level from the following:Safety stock: 1000 unitsConsumption per week: 500 unitsIt takes 12 weeks to reach material from the date of ordering"? |
| A. | 1000 units |
| B. | 6000 units |
| C. | 3000 units |
| D. | 7000 units |
| Answer» E. | |