*/*_"Calculate re-order level from the following:Safety stock: 1000 unitsConsumption per week: 500 unitsIt takes 12 weeks to reach material from the date of ordering"?

A. 1000 units
B. 6000 units
C. 3000 units
D. 7000 units
Answer» E.