1.

"Calculate re-order level from the following:Safety stock: 1000 unitsConsumption per week: 500 unitsIt takes 12 weeks to reach material from the date of ordering"

A. 000 units
B. 000 units
C. 000 units
D. 000 units
Answer» E.