1.

Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same

A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
Answer» B. R is correct but A is not correct


Discussion

No Comment Found