MCQOPTIONS
Saved Bookmarks
1. |
As per IS 456:2000, minimum period before striking form work for vertical surface of the columns |
A. | 1 days |
B. | 7 days |
C. | 14 days |
D. | 28 days |
Answer» B. 7 days | |