1.

Activity s,lack or float of any event on a PERT/CPM chart is represented by

A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event - earliest start time of the event
C. latest finish time of event - earliest finish time of the event
D. all of the above
Answer» E.