                                    ABC Ltd. of Mumbai supplied goods to XYZ Ltd. of Delhi under a contract for the goods to be delivered at the factory of the buyers. Goods removed from the factory of ABC Ltd. on 9-8-2019 and were delivered in the factory of XYZ Ltd. of Delhi on 16-8-2019. Invoice for the suppliers was raised by ABC Ltd. on 18-8-2019. Payment of the bill was received on 20-9-2019. The time of supply in this case under GST be taken as | 
                            
| A. | 9-8-2019 | 
| B. | 16-8-2019 | 
| C. | 18-8-2019 | 
| D. | 20-9-2019 | 
| Answer» B. 16-8-2019 | |