A type of estimate required if there is change amounting to more than 5% of the original value due to price hiking or change in specification, but does not include any major change in structural design is called |
A. | Detailed estimate |
B. | Revised estimate |
C. | Supplementary estimate |
D. | Rough cost estimate |
Answer» C. Supplementary estimate | |