1.

A power station has a maximum demand of 15000 kW. The annual load factor is 50% and plant capacity factor is 40%. Determine the plant capacity.

A. 18.75 kW
B. 1875 MW
C. 1875 kW
D. 18.75 MW
Answer» E.


Discussion

No Comment Found