1.

A generating station has a maximum demand of 500 MW. The annual load factor is 50 percent. The energy generated per annum will be:

A. 2.19 × 106 MWhr
B. 600 MWhr
C. 250 MWhr
D. 7.50 × 106 MWhr
Answer» B. 600 MWhr