1.

A power generating station has a maximum demand of 1000 MW. The annual load demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity.

A. 250 MW
B. 500 MW
C. 750 MW
D. 1250 MW
Answer» B. 500 MW