1.

A power station has a maximum demand of 15,000 kW. The annual load factor is 50% and plant capacity factor is 40%. Determine the reserve capacity of the plant.

A. 37.5 kW
B. 3.75 MW
C. 375 kW
D. 37.5 MW
Answer» C. 375 kW