MCQOPTIONS
Saved Bookmarks
| 1. |
A power generating station has a maximum demand of 1000 MW. The annual load demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity. |
| A. | 250 MW |
| B. | 500 MW |
| C. | 750 MW |
| D. | 1250 MW |
| Answer» B. 500 MW | |