A generating station has 500 MW maximum demand and annual load factor of 50%, capacity factor of 40%. The reserve capacity of the plant is |
| A. | 125 MW |
| B. | 625 MW |
| C. | 500 MW |
| D. | 725 MW |
| Answer» B. 625 MW | |