A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50
B. 0.66
C. 0.84
D. 0.95
Answer» D. 0.95